Dates for your diary
July 2026
Remaining tenants move in
Construction of the second phase would be completed and new tenants could move in.
May 2024
First tenants move in
Construction of the first phase would be completed and tenants could move in.
March 2024
Construction of Phase 2 starts
Subject to approved planning permission in September 2022.
13 September 2022
Planning Submission
The Council's planning committee will consider our application for Section 73 and Reserved Matters.
May 2021
Construction of Phase 1 starts
With Mayoral approval, the ground preparation works could start for the first phase in the spring.
April 2021
We appoint a builder
If the Mayor approves our plans, we will appoint a building contractor. The exact is to be confirmed. Our contractors are always members of the considerate contractors’ scheme.