30 November 2020

Planning Committee

The Council's planning committee will consider our application

April 2021

Mayor of London scrutiny

We hope that the Mayor will approve the project in early spring 2021.  The date of his decision is to be confirmed.

April 2021

We appoint a builder

If the Mayor approves our plans, we will appoint a building contractor. The exact is to be confirmed.  Our contractors are always members of the considerate contractors’ scheme

May 2021

Construction of phase 1 starts

With Mayoral approval, the ground preparation works could start for the first phase in the spring

May 2023

First tenants move in

The first phase could be completed and tenants could move in